A133 – Colchester – Clacton Route Improvements

Roadwork sign showing a man at work

Roadworks are due to start Monday 25 November to improve the Frating and Weeley Roundabouts on the A133.  This scheme is designed to improve the route from Colchester to Clacton and includes safety improvements between the two roundabouts.

The works are being carried out by Jacksons Civil Engineering and the works are due to complete next spring.

Specific traffic management arrangements, see: A133 Colchester to Clacton route improvements and share on the @essexhighways twitter feed.  The works are due to be carried out in a phased approach and involve lane restrictions.  A limited number of temporary overnight full road closures will be needed for specific pieces of work.

These works are reflected on one.network

See here for further information